Questions or Concerns Regarding this Work:
Mike Averett: Assistant Vice President for Facilities Management and Campus Operations, 812-488-2050, ma479@evansville.edu
Affected Dates:
Now through June 21, 2026.
Description of Work:
A contractor will remove older/unused equipment, install new pumps, new chillers, and new cooling towers
Impact for Campus:
-
There will be construction traffic (i.e., cranes and contractor trucks), dust, and noise.
-
Between March 9-13 there will be a large crane on campus removing cooling towers and chillers.
-
There will be buildings that will be warmer and colder throughout the construction timeframe. Shutdowns of existing chiller and boilers are required as work is completed.
Action(s) Required:
-
Please follow posted signage, caution tape and cones
-
Please do not park near the Central Plant, or in Ridgway Drive
-
Use caution near equipment and construction activity.
-
If your building becomes too hot (i.e., 80+ degrees) or to cold (62 or lower), please notify campus Facilities Maintenance.
Thank you for your patience as we build and maintain our beautiful campus.
To report a facilities emergency, call (812) 488-2775. |