Paving work along Lincoln Avenue between Rotherwood Avenue and Spring Street is ongoing. The updated construction schedule is as follows:

  • Surface Milling: Began on October 7

  • Patching: October 13

  • Asphalt Overlay: October 14–15

  • Striping: October 17

The city engineer says major work should be completed within these dates, with only striping possibly remaining afterward. Please plan for possible traffic delays during this time.